Interactive process simulation
One order. Four functions. One accountable decision.
Follow Order → Engineering → Procurement → Shipment, from an early risk signal to an approved action and a verified outcome.
- 01Inspect evidence
- 02Compare options
- 03Human approval
- 04Observe outcome
- 05Verify value
The order is at risk before the shipment meeting
The sample dependency calculation forecasts dispatch on 31 October: material arrival on 27 October plus four days for assembly, test and dispatch. The commitment is 27 October, leaving a four-day delay.
Order
SO-1042 / 24 valve assemblies
Ship by 27 Oct; order value ₹48,00,000
Source: ERP export, 15 Oct 2026 09:00 IST
Engineering
Drawing D-204, revision C
Review complete; authorized release still pending
Source: PLM task extract, 15 Oct 2026 09:15 IST
Procurement
PO-782 / actuator kit
Material arrival 27 Oct; earlier confirmed slot available at a cost
Source: Supplier confirmation, 15 Oct 2026 08:30 IST
Shipment
Assembly + test + dispatch
4 days after drawing release and material availability
Source: Approved routing, 14 Oct 2026